Updates and works taking place on site

‘Soft-stripping’ works are due to take place in the coming weeks. 

We have appointed Erith to undertake the ‘soft-stripping’ of the building. Works will commence on 15th June 2026 and are estimated to finish mid-January 2027.

‘Soft-stripping’ of a building does not require planning permission. We have met the local Environmental Health officer to talk them through our proposals.

The works will see the removal of internal fixtures and fittings, features such as door and walls, ceilings and floorings. Whilst we expect the soft-stripping proposed works to have very little impact upon our neighbours, we remain committed to keeping neighbours updated. We’re also hosting our first community liaison meeting where you’ll be able to discuss the upcoming works with the team on Tuesday 16th June on site at One Silk Street, EC2Y 8HQ from 5pm-7pm. Please arrive at 5pm. The meeting will conclude by 7pm.

This website will serve as a hub for updates on site activities – please do sign up to the mailing list at the bottom of this page to receive future updates.

One Silk Street divider one

Sign up to our mailing list

Stay up-to-date with the latests news about the project.

Mailing list

Disclaimer: We use ReCAPTCHA to help protect this website from spam and abuse. Any information you provide us with, should you wish to do so, will be held securely and processed in line with our privacy policy. You will only be contacted in relation to the project.